Hidrelétrica

 

Start of Construction

1954

Start of Operations

1959

Dam Height

22m

Dam Length

345m

Reservoir Volume

192,7hm³

Installed Power

7,2MW

Generating Units

1

Learn more about it

Cajuru Small Hydroelectric Power Plant (PCH) is installed on Pará River, in the municipalities of “Carmo do Cajuru” and “Divinópolis”, state of Minas Gerais, and has a generating unit of 7.2 MW. The right bank is located in “Carmo do Cajuru” and the left bank is located in “Divinópolis”. This dam was designed with the main purpose of storing water for the regular functioning of “Gafanhoto” Hydroelectric Plant, located downstream. The reservoir has an area of 23.27 km².

Cajuru SHP Dam is composed of the following structures: Right Bank Concrete Dam, Surface Spillway with Controlled Sill, Left Bank Concrete Dam and Left Bank Earth Dam.